Wednesday, December 9, 2015

5.12.15, pp with infra-tec-gh to inspect work done

P.P went with infra-tec-gh to inspect work done on solar construction and the testing of pump....
work still progresses with fencing for solar panels, fetching station, and pillars for water storage tanks...

27.11.15,solar work done and testing

on the 27 Dec. 15, infra-tec-gh, reps Emmanuel Panford & Sulley Mustapha Ahmed got solar work done and tested the pump for water flow and intact water got flowing......

https://drive.google.com/folder/d/0BwUPsWGsMLpBaTZnN1BubE9QTUk/edit

30.11.15,nfratec-gh with pp to Nkwantakese

on this day Monday 30th December, 2015
infra-tec-gh colleges went together to nkwantakese to visit projects :
it150929
it150928

Thursday, November 26, 2015

Cable laying...26.11.15

Infra tec .........engineers digged hole path for PVC pipe and cable laying for motor control and float switching....
Still waiting for inverter to test pump with solar electricity...
https://drive.google.com/folder/d/0BwUPsWGsMLpBaTZnN1BubE9QTUk/edit

Solar work installs contd 23.11.15

Solar installation work done ....
After installation.... Testing the inverter output voltage gave 500v which is detected the inverter was faulty....
Inverter is sent to distributor for rectification......
https://drive.google.com/folder/d/0BwUPsWGsMLpBaTZnN1BubE9QTUk/edit

Sunday, November 22, 2015

infra-tec-gh solar installation... 21.11.15

Solar installation work started....
Time start .10:30am
End .6:00pm ...

Work did:
drilling holes for fixing panels,panel fixing,fixed solar panel charge controller,inverter and batteries.
........work continues ...on Monday .23.11.15
What is to be done lighting, passing cables & testing pump...
https://drive.google.com/folder/d/0BwUPsWGsMLpBaTZnN1BubE9QTUk/edit

Monday, November 16, 2015

El equipment...,16nov.2015

Infra-tec-gh...went to purchase electrical equipment n cables for El
https://drive.google.com/file/d/0BwUPsWGsMLpBNzFHVFY4bi1nUGM/view?usp=docslist_api

Tuesday, November 10, 2015

Nov.10.15

Project work to be continued in due time  in Mampong ....
Solar work construction equipment has been ordered ....waiting to arrive...

Friday, October 9, 2015

oct. 9, 2015

filling in of contract dates, dates of work start and completion in the tasks list.
start :12 pm
stop: 3:30pm

Wednesday, October 7, 2015

Tuesday oct. 6, 2015

I went back to the site and the estimator for the electric house  from electricity company came on Tuesday for site inspection...but he requested for the site plan for the land of the project in order to determine where the pole should be for connection of the electric energy meter. if that isn't provided then I have to provide that before he progresses to give estimate everything...
the estimator rescheduled for next week to provide the site-plan then he can proceed to estimate.
the mason continues with plastering........

Estimate for the waterstation and pillars for the polytank was also made...

Monday oct. 5, 2015

I returned to Kyeremfaso-Mampong, project site to fix pipes for electric wiring and plastering pipes.
the mason also started work with plastering on electric house.

https://drive.google.com/open?id=0BwUPsWGsMLpBQVlsb1pWWjhfODA

https://drive.google.com/open?id=0BwUPsWGsMLpBQnZmVWN4MEtHU2M

https://drive.google.com/open?id=0BwUPsWGsMLpBZ1c5ZUtaWXJYdkk

Friday oct 2, 2015

Went to Mampong and together with Gloria to the electricity company to submit the letter, land marking to the manager's office.
Gloria signed as the caretaker for her name to be on the bill for payment and I witnessed it...the estimator was scheduled to examine the site on Tuesday Aug 6, 2015.
I came back to kyeremfaso to monitor work progress and continued with fixing boxes for electric house.
electric house roofing was completed on Friday Aug 2,2015.

https://drive.google.com/open?id=0BwUPsWGsMLpBS0lnMTlfRG40cGM

https://drive.google.com/open?id=0BwUPsWGsMLpBZlVrNHBoOUJZXzg

arrival at kyeremfaso at 9:30am
departure: 6:00pm

Wednesday, September 30, 2015

30.sept.2015

Work for electric house has got to roofing stage...
Electric work has also began ...with chiselling n conduit boxes fixed for  lighting, socket n motor ...

https://drive.google.com/folder/d/0BwUPsWGsMLpBfnFYZUdMc3ZBazJYa3plcDJZRlY3SE1mdkplOEJJMFc2eF8tcHBkamxMb3M/edit

Thursday, September 24, 2015

Sept.24,2015

Work progress from Mampong...
Plastering work for electric house still in progress ...yet in lintel stage....

https://drive.google.com/thumbnail?id=0BwUPsWGsMLpBaGZoVGVDQi1FdEk&authuser=0&v=1443140906539&sz=w348-h260-p-k-nu

Sunday, September 13, 2015

overview of hydraulic drawing for drilling, sept.10, 2015

overview of hydraulic drawing was done....partway
to be completed later....


time spent: 1hr




https://drive.google.com/open?id=0BwUPsWGsMLpBQmQ1U2QwM3dFbTA

land survey report collection, sept.7, 2015

*collection of geophysical land study on drill site report
collection date ;sept.7,   1:30pm
collection made by Emmanuel Panford
received from : kwabena Agyenim


*payment of ghc1300 was made......
 recipient: kwabena Agyenim


*expenses: transportion
ghc 10

geophysical study , sept.6, 2015

geophysical study was done on sunday by geologist......

meet up with geologist, 4th sept. 2015

meeting with geologist
things discussed:
*negotiation about geophysical study of probable location for drilling
cost reduces from ghc1500 to 1300.
location :Ghana water company ltd.


*proceeded to go with a geologist representative to show the site location of mampong water station.
*expenses by; geologist....

180124..it_gh Mampong

Mampong sensor fix... I went to fix Mampong sensor control switch for the automation system.. . This was due to inaccuracy to sensor level...