Went to Mampong and together with Gloria to the electricity company to submit the letter, land marking to the manager's office.
Gloria signed as the caretaker for her name to be on the bill for payment and I witnessed it...the estimator was scheduled to examine the site on Tuesday Aug 6, 2015.
I came back to kyeremfaso to monitor work progress and continued with fixing boxes for electric house.
electric house roofing was completed on Friday Aug 2,2015.
https://drive.google.com/open?id=0BwUPsWGsMLpBS0lnMTlfRG40cGM
https://drive.google.com/open?id=0BwUPsWGsMLpBZlVrNHBoOUJZXzg
arrival at kyeremfaso at 9:30am
departure: 6:00pm
As a chance for Knowledge and culture exchange EMMANUEL and DAVID have a programme with Ruth in Switzerland from 20. April till 17. Mai 2017
BLOG-Overview ... David in Switzerland http://gsep4david.blogspot.ch/ ... Emmanuel in Switzerland http://gsep2.blogspot.com (this BLOG)
Subscribe to:
Post Comments (Atom)
180124..it_gh Mampong
Mampong sensor fix... I went to fix Mampong sensor control switch for the automation system.. . This was due to inaccuracy to sensor level...
-
Fault tracing at Okubi... Borehole pump not working.... Checked power.... Pump need to be removed n checked as well...
-
Infra-tec had a meeting to decide on how and when to approach the hotels with our proposals
-
Work progress still ongoing ..... Now with block laying, And carpentry works done for waste ....and pillar works done as well... ...
No comments:
Post a Comment