Solar installation work started....
Time start .10:30am
End .6:00pm ...
Work did:
drilling holes for fixing panels,panel fixing,fixed solar panel charge controller,inverter and batteries.
........work continues ...on Monday .23.11.15
What is to be done lighting, passing cables & testing pump...
https://drive.google.com/folder/d/0BwUPsWGsMLpBaTZnN1BubE9QTUk/edit
As a chance for Knowledge and culture exchange EMMANUEL and DAVID have a programme with Ruth in Switzerland from 20. April till 17. Mai 2017
BLOG-Overview ... David in Switzerland http://gsep4david.blogspot.ch/ ... Emmanuel in Switzerland http://gsep2.blogspot.com (this BLOG)
Subscribe to:
Post Comments (Atom)
180124..it_gh Mampong
Mampong sensor fix... I went to fix Mampong sensor control switch for the automation system.. . This was due to inaccuracy to sensor level...
-
time: 9:30am - 17:45pm places - Rainach and Basel football stadium 🔼 Today was our last Sunday in church and we attended it in Rainac...
-
Time - 12:00pm - 8:30pm Venue - Arisdorf & Solothurn(Witterswil) 😇 Today after breakfast, we went together with Auntie Ruth to h...
-
Time: 8:45am - 18:45pm Baselstrasse Aesch BL - Haeusler âž½ After breakfast today, we visited the kids of the school where auntie Ruth...
No comments:
Post a Comment