1/ today we went to okubi to do actual measurement of length and height to fit in the estimate ....
2. the drawing for the automation system is also prepared.....
location surveying and fountain diagnosis was done by I- Emmanuel. Sulley and David.
As a chance for Knowledge and culture exchange EMMANUEL and DAVID have a programme with Ruth in Switzerland from 20. April till 17. Mai 2017
BLOG-Overview ... David in Switzerland http://gsep4david.blogspot.ch/ ... Emmanuel in Switzerland http://gsep2.blogspot.com (this BLOG)
Monday, September 26, 2016
Estimate update-gh-it_10916_Okubi
I updated the estimate done for okubi hotel
https://drive.google.com/open?id=0BwUPsWGsMLpBc1lMcF9jVHdRWkE
https://drive.google.com/open?id=0BwUPsWGsMLpBc1lMcF9jVHdRWkE
Tuesday, September 20, 2016
Estimate for gh-it 160916-Okubi
1/ estimate for the water automation system at okubi hotel done .......
yet to be given to the management for acceptance.\\\\\
https://drive.google.com/open?id=0BwUPsWGsMLpBUEphTllPTlB4cU0
yet to be given to the management for acceptance.\\\\\
https://drive.google.com/open?id=0BwUPsWGsMLpBUEphTllPTlB4cU0
Friday, September 16, 2016
okubi contract aquisition
Friday, September 9, 2016
150929b_nkwantakese_bell and lamp channel dig
Digging pipe channel to fetching station for the bell and bell switch was done .....
together with Sulley and David....and as well saw work go on with the waste tank.......
together with Sulley and David....and as well saw work go on with the waste tank.......
Wednesday, August 17, 2016
fetching notice and fault trace.(*Aug.16.16
Agenda:
fetching notice and fault trace
Time: 12pm
hours used - 1hr
Task :
I went to paste a A4 sized notice beside the fetching wall indicating time of fetching water and traced a fault identified last time of visit.
Fault detected and diagnosed.
fetching notice and fault trace
Time: 12pm
hours used - 1hr
Task :
I went to paste a A4 sized notice beside the fetching wall indicating time of fetching water and traced a fault identified last time of visit.
Fault detected and diagnosed.
Thursday, May 5, 2016
completed work 150330
Date :
5.05.16
Time:
11 am
Task:
1. Automation system for pump complete
2. Plaque fixing
3. Fetching station gutter for water direction passage...
Job by:
Emmanuel ,Sulley and plasterer....
* all three task done with automation working correctly...
Finished at 6pm....
5.05.16
Time:
11 am
Task:
1. Automation system for pump complete
2. Plaque fixing
3. Fetching station gutter for water direction passage...
Job by:
Emmanuel ,Sulley and plasterer....
* all three task done with automation working correctly...
Finished at 6pm....
Subscribe to:
Posts (Atom)
180124..it_gh Mampong
Mampong sensor fix... I went to fix Mampong sensor control switch for the automation system.. . This was due to inaccuracy to sensor level...
-
Mampong sensor fix... I went to fix Mampong sensor control switch for the automation system.. . This was due to inaccuracy to sensor level...
-
Work still ongoing now with concreting floor... Fixing waste pipes and iron for waste
-
Today ....things were cleared and space prepared for the training school stuff... Hope for the future....we prepared ...five(5) PCs. ...one...